Do inspections at places where defects emerge or where they are costlier to find, instead of conducting inspections after every operation. In job shops, this typically refers to four places – that is, receiving, first piece inspection following a new setup, operation cutting important features, hand-off before outsourcing, and last inspection. Anything other than these four is optional and needs to prove itself worthy of being checked.
This is important because Odoo can help you conduct inspections easily. You can perform it in a matter of clicks while performing various operations in Odoo’s Quality app. Half a month later, the operators would still be clicking “Pass” without reading what is being presented to them. In the end, checks are accomplished in three seconds, including those of no importance.
Why Placement Matters More Than Volume in Job Shops
The production line can conduct its inspections every now and then, when working for many years in producing a single product. The job shop, however, should perform the inspections constantly.
Generally speaking, you may be in charge of a situation where you run an aluminum bracket in the morning, process a stainless-steel shaft after lunch, and repeat the procedure the next day. There is always a new setup, a new tool to be used, and a new possibility to make this mistake in the process.
That’s the main reason placement plays a more important role than volume. In particular, if the incorrect tool is set at a Haas milling machine, it is the tool that will create bad parts continuously until the problem is identified. If this person is the final inspector, the whole batch of goods is ruined, and the time utilized by the machine and material used are wasted.
There is much more money given to ASQ. As information from ASQ shows, many organizations incur quality-related costs of around fifteen to twenty percent of their sales revenue, and sometimes even higher. They incur those costs because problems are discovered late, such as scrap, rework, rush remakes, and returns.
The idea is not to have more checks but to have them at points where the defect is found or where it will cost more money to identify it late.
How Odoo Ties a Quality Control Point to the Routing

A quality control point (QCP) in Odoo means a rule that states that a check must be executed when an operation is performed on a product. According to Odoo’s documentation on quality control points, each QCP is built from a few settings:
- Products or product categories: which product or brand(s) trigger a check. If left empty, it will apply to all.
- Operation: what type of operation should trigger the check; receipt, manufacturing or delivery, for example.
- Works order operation: in terms of manufacturing, it is possible to make the audit at a specific point of the manufacturing routing such as “Op 30 – CNC finish mill” not the whole manufacturing order.
- Control per and frequency: whether check is executed on every operation
- Type: specific details on what the operator performs—such as pass/fail, measures, gives commands, or takes a picture.
Work order operation field is where the real value can be derived in a machine shop. It is what allows one to see a check at the right stage of a process rather than as a generic task at the end of a procedure. Since quality control processes are directly relying on operations, inspection maps are taken as valuable as the routing behind them.
Some machine shops implement the corresponding structure with the participation of their Odoo implementation partners, such as Glorium Technologies, in order to learn how to modify the process of controlling specific points after learning about their significance for different operations.
The Inspection Map: Five Places Checks Earn Their Keep
This is a simple check map. Treat it as a simple guide that can help you to learn how the check map works.
| Inspection stage | What to check | Typical gauge or method | Odoo setup |
| Receiving | Bar stock size and material cert, casting dimensions, outsourced coating thickness | Calipers, mill cert review, coating thickness gauge | QCP on the receipt operation, pass-fail or measure, take a picture of the cert |
| First article after setup | Every dimension on the drawing for the first good part | Micrometers, height gauge, CMM for complex parts | QCP on the first machining work order step, worksheet or several measure checks |
| In-process on critical features | Bores, threads, true position, surface finish on functional faces | Bore gauges, thread gauges, profilometer | QCP on the specific work order operation, measure with norm and tolerance |
| Before outside processing | Dimensions that heat treat or plating will lock in or hide | Micrometers, thread gauges, visual for burrs | QCP on the last internal step before the part ships to the vendor |
| Final inspection | Drawing callouts, cosmetic requirements, quantity, marking | Mix of hand gauges and CMM, visual | QCP on the final operation or the delivery, pass-fail plus measure on key features |
Some points require further clarification.
First article inspection
First article inspection (FAI) is perhaps the most valuable check in a job shop in the sense of preventing potential errors from happening. In the aero industry, FAI is carried out according to AS9102, with Form 3 being a document used for traceability of all dimensions and notes in the drawing.
Before outside processing
Before outside processing is often omitted but the costs of doing so can be extremely high. Once a part gets sent for heat treatment, coated, or zinc-plated, it is no longer easy to change it.
A bore that measures 0.02 mm below the required size can be fixed before it is hardened, but afterward it either has to be ground or thrown away. Coating also adds thickness to the part, which means that a thread that just met requirements can fail in the process.
Choosing the Type of Check and Its Frequency
A type of check has to match what the operator is able to actually do on the machine.
- Measure is for anything that has tolerance number. It means the operator receives a norm (the value from a drawing) and tolerance, then provides a micrometer measurement. The check is passed only if the measurement falls within the tolerance. Use it for bores, length, and diameter that have strict tolerances.
- Pass-fail is for checks of quality: thread gages, go-no-go pins, visual burr checking, “cert matches PO”. It is fast, but does not provide much information, and hence not recommended.
- Instructions check consists of a check step that has to be confirmed by the operator. It works well for such instructions as “get rid of any burrs”.
- Take a picture is for checking received documents (photo of the mill cert or packing slip).
- Worksheet check provides one more solution, around a form which is good for FAI, which includes many checks combined into one check.
Frequency: every part, sampling, or after a change
Odoo assigns a control frequency to each QCP.
“All” requires checks every time the conditions allow this.
“Randomly” means one inspection for certain percentage of operations.
“Periodically” refers to the schedule like once per given period of days, weeks, or months. “On-demand” means someone has to request it manually.
“Control per” settings define whether the inspection considers all the operations, every article being manufactured, or a certain percentage of the quantity.
In practice, it is necessary to adjust frequency according to the risk factors:
- Every part for safety critical features, short runs, or cases when one bad part stops assembly.
- Sampling (for example, percent of the quantity) for stable processes, long runs with proven capability.
- After change of tools or new setup for applications when cutting tools wear, like boring bar in tight bore. Odoo does not find out about the tool change by itself, therefore it is usually done by on-demand check performed by the operator or special first-piece check on the operation which has been restarted.
Don’t make a mistake of using the full scope of frequency without presenting anything that happened afterwards.
When a Check Fails
In Odoo, one will find a “Message If Failure” tab present in QCP for measure, pass-fail and other types. Here one will write what the operator will need to do in case a part fails. This message stands for the reaction plan which should be documented in the following manner:
- Stop the machine and keep the parts produced since the last time a control was carried out.
- Inform the quality supervisor by creating a quality alert, and, if necessary, by attaching the photo.
- Find out the reasons for a failure the last time the part was checked by re-measuring the last good part.
- Make a decision on whether to dispose of the part, recreate it, or directly use it in a product and keep the record of it.
Quality alerts are responsible for the investigation. They give the team a record of what failed, on which part and operation, and what was done about it. Over some time, they will show which operation troubles are frequently dealt with so that one can carry out checks whenever alerts occur or simply get rid of unused alerts.
Here traceability aspect is important as well. If one keeps the record of batches or serial numbers for its bar stocks and finished components, than a failed inspection at the end can be traced back to a heat lot or to a batch of receiving report. For a shop involved in performing regulated activities, a track of that failed component to its material certificates is the first concern of the customer’s auditor.
Causes of Noncompliance with Quality Checks
Most setups that have failed inspection fail not because of the software but because of inconsistent checks.
Two many checks. A routing that involves ten operations has a check being performed on every operation. The result is that the operators learn to get through the checks without paying attention. The checks need to be cut down to the most important five different checks.
Checks that cannot be done at the machine. A flatness check being according to the design at the lathe with only calipers in the environment will either end up having no check or will have a random number filled in. The checks where you would need a CMM machine or a surface plate should be either routed there.
Poor tolerances. If tolerances entered manually from the last revision do not correspond with the actual drawing, they do more harm than good. Make sure that your quality control points comply with the current revision of the drawing and at least review them every time there is a change.
Unclear instructions. “Check the part” does not mean much to the operator. “Use 25-50 mm bore gauge to measure bore A at both edges and enter the biggest value” is clear.
Where to Begin
When preparing quality control points for the first time, it should not be done all at once. Start with:
- Receiving check on material certificates and thickness. If the material is wrong, no process would be successful.
- First-article measurement or sheet check at the first step of machining for this revision.
- Check at the final internal operation before leaving for heat treatment/ electroplating.
Run this check for a month, analyze all alerts, and then add new checks only where alert systems indicate possible defects.